A £9 million upgrade of Inverness Railway Station and the line to Kyle of Lochalsh is to get underway this weekend (November 28).
The work will last three weeks, with the line between Dingwall and Kyle of Lochalsh will close until December 18.
During the closure, Network Rail teams will be working at locations across the route. At Inverness Railway Station, track, and sleepers at platforms 5 and 6 will be replaced, along with equipment that allows trains to move from one track to another.
Around 7km of track will also be renewed at several locations, including between Welsh’s Bridge and Rose Street level crossing in Inverness, at Achanalt and Rosebank near Achnasheen, and between Strathcarron and Stromeferry.
Engineers will renew several culverts between Dingwall, Achnasheen, and Stromeferry to improve drainage and help protect the railway during bad weather. Repairs and track renewals will also be carried out at several railway bridges, including Carron Viaduct.
Gary Hopkirk, route director at Network Rail Scotland, said, “The Kyle line is an important connection for communities and the many visitors who use it each year, so we know there is never an ideal time to close it.
“This three-week closure gives us the opportunity to complete a significant amount of work in one go, helping to keep the railway safe and reliable for years to come.
“We’re asking passengers to plan ahead and check their journey before travelling, and we thank everyone for their patience while we complete these improvements.”