Tummel Bridge Power Station reopens following £50m refurbishment

PERTHSHIRE’S iconic Tummel Bridge Power Station has officially opened following a £50 million refurbishment by SSE Renewables.

The site, which is in the centre of the overall Tummel Valley Hydro Scheme cascade, is once again generating renewable electricity following the installation and energisation of two new hydro-electric power turbines.

SSE Renewables’ £50 million investment, one of the largest ever for its hydro fleet, has seen the hydro station re-powered and its potential generation output increased from 34 to 40 megawatts (MW) during optimum conditions.

Inverness-headquartered Global Infrastructure operated as principal contractor for the duration of the project. Other Scottish-based firms included Global Energy Group at Port of Nigg in Cromarty Firth, which was responsible for Forebay Stoplog fabrication and Tailrace Gate modifications, while Rosyth-based KAEFER oversaw corrosion protection works. The team at Konecranes Demag UK, of East Kilbride, modernised and upgraded the 90-year-old 120-tonne station crane, while McDonald Scaffolding from Invergordon was scaffolding contractor.

Over the course of the site works, the project has seen over 700 different people working for approximately 30 different contractors from all over Scotland, the UK and Europe, as well as hundreds of visitors to Tummel Bridge Power Station.

The work involved the replacement of the station’s two original ‘Camel Back’ twin-runner, horizontal Francis hydro turbines, which were installed in 1933, with new modern runner technology.

SSE explained the new technology increases water flow, enabling the increase in generation output at the plant and extending the hydro power plant’s working life by at least 40 years. This means Tummel Bridge Power Station will be running in the power system of 2050 and will play a continuing role in harnessing homegrown hydro power for a net-zero future in Scotland and the UK.

First minister John Swinney

The first of the new Tummel units started generating in March this year with the second energised during testing in May 2024. First minister John Swinney, who is MSP for Perthshire North, officially powered up the units at a ceremony hosted by SSE.

He said, “The reopening of Tummel Bridge Power Station marks a significant moment in Scotland’s renewable energy journey. This £50 million investment ensures that one of our country’s iconic hydro stations will continue to play a crucial role in generating clean, sustainable energy. The modernisation of this historic site demonstrates how Scotland’s natural resources can be harnessed to support our transition to net zero, while also preserving an important part of our industrial heritage. I congratulate everyone involved in successfully bringing this project to fruition and look forward to the long-term benefits it will deliver over the coming decades.”

Martin Pibworth, chief commercial officer at SSE, added, “The Tummel Bridge refurbishment programme is one of the largest single investments we’ve made in our existing hydro fleet, and clearly supports hydro’s vital role in the path to achieving UK and Scottish net zero carbon emissions targets. Tummel Bridge has been a part of the energy landscape for generations and this investment will ensure this iconic and historic site continues to play a crucial role in Scotland’s energy mix for decades to come.”

David MacDonald, MD of Global Infrastructure, added, “I am proud Global Infrastructure played a key role in the delivery of this complex project and look forward to further to assisting with similar works in the future. The project was a great example of teamwork and collaborative working as a project team. We look forward to working together with both Voith and SSE in the future.”

Stantec, with bases in Edinburgh and Glasgow, led on civil design as well as supporting the engineering team. Craig Scott, director of hydropower at Stantec, commented, “Refurbishment schemes like Tummel Bridge are an integral piece of our low carbon future. Retrofitting existing energy assets with modern, highly efficient equipment, rather than rebuilding them, brings added value for our clients as well as the communities they serve. Both in terms of project costs and carbon reduction.”

Voith Hydro, a specialist manufacturer of hydropower turbines and generators, led on the mechanical and electrical (M&E) elements of the project. Dr. Christian Bender, CFO of Voith Hydro Europe, said, “The trusted and long-term partnership between SSE and Voith Hydro has been the foundation on which our respective expert teams have worked closely together during the design stage as well as the installation and commissioning phase. This partnership has been the driving force behind the project’s success and serves as another example of the excellent relationship between both companies.”

The project also contributed to SSE Renewables’ sustainability strategy by minimising the creation and disposal of waste through circular solutions. The civil works involved the removal of around 4,000 tonnes of concrete and 1,000 tonnes of steel, almost all of which were recycled or reused.