Levenmouth rail project to see installation of active travel bridge

Network Rail
Network Rail

NETWORK Rail is set to crane a 129-metre active travel bridge into position to connect Methilhill and Cameron Bridge.

Nine pre-fabricated sections – including bridge piers, staircase sections, and four spans of the bridge deck – will be installed during the work.

The installation had originally been planned ahead of the opening of the Levenmouth rail link but was delayed due to the company building the bridge going into administration this year.

Complex discussions with the administrator to release the part-built structure, as well as the need to source a new supplier, compounded that delay, Network Rail explained.

Now, with plans in place to complete the work, no parking and no waiting zones have been introduced on Poplar Road and Kirkland Walk until 16 September so that work vehicles can access the site.

Tommy McPake, senior programme manager at Network Rail, said, “The team has worked hard to build the alternative walking route and then to deliver on the revised timeline to get the structure complete and site prepared for the bridge installation. While it was disappointing not to have the bridge in place ahead of the opening, it was due to circumstances beyond our control that could not have been foreseen.

“We hope the new bridge allows the community in Methilhill the opportunity to fully join in the excitement the return of the passenger service to Levenmouth has created. We’re now very close to completing the connection to their local station which will enable them to easily access all of the opportunities the railway delivers.

“It is always exciting to see the crane lift the bridge into position to create what will be a very impressive looking structure that will support active travel in the area. We are grateful to the surrounding communities for their cooperation as we bring the bridge sections to site and look forward to completing the work in the coming weeks.”