SCOTTISH Water has published time lapse footage of the recently completed repairs to a major sewer pipeline by Carnoustie Golf Links.
The footage showcases the work of specialist contractors in delivering the works during challenging conditions.
Scottish Water explained the damage caused by stormy seas during high tides at the end of October presented a ‘sting in the tail’ of Storm Babet, affecting many of the same communities which had already experienced extreme flooding impacts at the height of the storm.
By Carnoustie Golf Links, the seas broke through coastal defences and washed away a 30 metre section of a sewer pipeline and the surrounding land. The affected area continued to be battered by the sea and inundated twice daily by the tide as repair efforts began.
Support was on hand from local civil engineering contractor, Geddes, who were released from planned work by Angus Council to begin the recovery effort as soon as conditions permitted.
Within days, work progressed far enough to allow a specialist team of engineers from Morrison Construction to begin the repair of the pipeline itself, including the installation of 40-metre-long sheet piles to supplement the restored and reinforced rock armour. Scottish Water added that the pace of the work is reflected in the time lapse footage recording the coordinated efforts of both Morrison and Geddes teams.
The work was overseen by Scottish Water’s PFI partner Veolia, alongside a simultaneous 24 hour operation to minimise the impact of the incident on the local environment and manage the operation of the Waste Water Treatment Works at Hatton.
The combined work of all the teams involved, supported by Carnoustie Golk Links, Angus Council and members of the public, enabled the sewer network to be returned to normal operation within less than two weeks.
Scottish Water’s PFI performance manager Craig Carr said, “Given the scale of the damage that had been wrought by the forces of nature, it is a huge credit to the whole team on site that flows could be restored via the pipeline within 10 days of the damage occurring. The footage does not really do justice to the very difficult conditions on site in the first few days, when high tides and waves continued to batter the area. However, it shows the pace of the combined efforts once the protection of rock armour had been largely restored.
“As we adapt to the wide-ranging impacts of climate change on our infrastructure, we know that we will face more challenges like this. We aim to improve our ability to anticipate and prevent damage where we reasonably can, but our ability to respond quickly when required will always be a key element of our resilience. The first-class support from our supply chain and from other key partners, which was strongly in evidence at Carnoustie, stands us in good stead.”
Drew Mackie, construction manager at Morrison Construction, added, “I am so proud of our team who were deployed to resolve the damage to this vital sewer infrastructure. The sewer was quickly returned to normal working order whilst the team battled severe weather conditions in a marine environment under tight timeframes. The quality and resilience the team have shown is exemplary and I want to express my appreciation to everyone who helped in this emergency situation.”