Paisley business takes on ‘unique and complex’ power station scaffolding project

JR Scaffold Services has started work on a major re-insulation and re-cladding project at Cockenzie Power Station in East Lothian.

Acting on behalf of Luddon Construction, the Paisley-based scaffold business will be working at the site as part of a wider project by Scottish Power Energy Networks (SPEN), and has been tasked with removing asbestos insulation and re-insulating the perimeter of the internal and external walls of the power station in its entirety, which actively supplies power to a large percentage of Scotland.

Scaffolding will be built in phased sections – some reaching up to 23 metres high – built both from the ground, and also from the higher mezzanine levels, to ensure all areas of the site are inspected for the hazardous material and re-cladded.

The project is planned to run for approximately 80 weeks and within each phase of the project, JR Scaffold Services explained that scaffold works will be timed in line with specifically planned power outages to allow the team to maximise the work.

Due to the complexities of the project, almost three years of detailed planning was carried out.

John Horne, MD at JR Scaffold Services, said, “This unique and complex scaffolding project will bring some unusual challenges, including a bespoke scaffold build programme, the handling and removal of hazardous material, and carefully managing the timing of the project around planned power outages to minimise disruption. We are proud to work closely with Luddon Construction to ensure that we can complete this project on time and as safely and efficiently as possible.

“JR Scaffold have committed a considerable amount of time and investment, gaining the appropriate accreditations to allow us to bid for such major projects such as this that involve the removal of hazardous asbestos, so we’re looking forward to provide our skillset to support Scottish Power Energy Network on this vital project.”