Engineers work through the night to install 75-tonne structure at Uddingston Station

Network Rail

NETWORK Rail and Story engineers worked through the night on Saturday to install a new fully accessible footbridge and lift towers at Uddingston Railway Station.

The total weight of the whole structure is 75-tonnes, with the largest component – the bridge deck – weighing 15-tonnes. A 230-tonne crane and a 60-tonne crane was used to lift the superstructure into place.

Network Rail

Forming part of the access for all scheme, the project will look to make it easier for people with impaired mobility or those travelling with luggage, children, or bicycles to access platforms at stations across the UK.

Work is continuing on the project with the footbridge and lifts set to be opened to the public shortly after the old footbridge is removed in June, Network Rail said.

Susan Menmuir, scheme project manager at Network Rail, said, “Delivering a structure of this size onto the platform is a huge achievement. We’ve worked collaboratively with our principal contractor Story while liaising with ScotRail, South Lanarkshire Council, and British Transport Police to ensure this was done safely and on time.

Network Rail

“Working through the night provides the safest environment for our teams to work in and the least disruption for passengers. We thank the public for their cooperation and understanding while the car park was closed to allow these crucial works.

“There is still a lot to do before passengers will be able to use the footbridge and the lifts, but we hope everyone living nearby and using the station is pleased with the progress so far and is looking forward to the benefits of having a fully accessible station.”

Councillor Kenny McCreary, who represents Uddingston and Bothwell, added, “I would like to compliment Network Rail and their partners on delivering the upgrades to Uddingston Station.

“Throughout the work, they consulted with residents, local groups and elected members and their communication was first class. The work has been completed on schedule and will support those with mobility issues, with small children and those with luggage through installation of a lift to allow access to both platforms.

“In addition, Network Rail and their contractors have been sympathetic to the expectations of the local horticultural group, Grow Uddingston, who make the station one of the prettiest in Scotland, especially in spring and summer when flowers are in full bloom.”